ALL FPSC PAST PAPERS MCQS OF BASIC ARITHMETIC 1998 TO 2019
چار آپشن میں سے کسی ایک پر کلک کرنے سے جواب سرخ ہو جائے گا۔
- 14
- 8
- 12
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
Explanation
15 men complete the work in 8 days
Total work = 15 men * 8 days = 120 man-days
Now, to complete the work in 10 days:
120 man-days / 10 days = 12 men
- 370 men
- 360 men
- 380 men
- 410 men
اس سوال کو وضاحت کے ساتھ پڑھیں
Explanation
1/240 * n * 4 = 6 becomes:
1/240 * 360 * 4 = 6
we simplify to get:
6 = 6 confirming that our calculation of the number of people required is good.
the answer is that it would require 360 men to fill 6 holes in 4 months.
- 114 men
- 140 men
- 180 men
- 160 men
اس سوال کو وضاحت کے ساتھ پڑھیں
Explanation
If 40 men can build 4 buildings in 12 months we can divide 4/12 which is 1/3..
40*3 is 120 men for 4 buildings and 120 is divided into 4 we get 30 men for 1 building..
so for buildings 30*2 = 60
120+60 is = 180
- 52 1/2
- 60
- 61
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
Explanation
105 men complete the work in 45 days
Total work = 105 men * 45 days = 4725 man-days
Now, 90 men will complete the work:
4725 man-days / 90 men = 52.5 days
- 40
- 50
- 61.25
- 80.50
اس سوال کو وضاحت کے ساتھ پڑھیں
Explanation
Find how many man-days to complete the road:
70*35 = 2450 man-days
Let d = days required for 40 men to do it.
40d = 2450
d=402450=61.25
- 800
- 700
- 600
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
Explanation
9% of x = 63
0.09x = 63
x = 63 / 0.09
x = 700
- 29 days
- 26 days
- 22.86 days
- 27 days
اس سوال کو وضاحت کے ساتھ پڑھیں
Explanation
Step 1: Find total work in man-days
80 men complete the bridge in 20 days.
Total work =80×20=1600 man-days
Step 2: Find time for 70 men
Time=Total work/Number of men=1600/70
Time=22.86 days
- 40%
- 60%
- 43%
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
Explanation
Percentage of games won = (Games won / Total games) * 100
= (18 / 30) * 100
= 0.6 * 100
= 60%
- 60 days
- 30 days
- 29 days
- 23 days
اس سوال کو وضاحت کے ساتھ پڑھیں
Explanation
- Men × Days = Total Work
- Formula
- M1 X D1 = M2 X D2
- 60 × 40 = 40 × D
- D = (60 × 40) ÷ 40
- D = 60 days
Last updated on 12 NOV 2026
- 40 days
- 50 days
- 30 days
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
Explanation
40 men finish the work in 25 days
Total work = 40 men * 25 days = 1000 man-days
Now, 25 men will finish the work:
1000 man-days / 25 men = 40 days