40 men can finish a work in 25 days. In how many days, 25 men will finish the same work?
  1. 40 days
  2. 50 days
  3. 30 days
  4. None of these
Explanation

40 men finish the work in 25 days

Total work = 40 men * 25 days = 1000 man-days

Now, 25 men will finish the work:

1000 man-days / 25 men = 40 days