If 15 workers can complete a job in 12 days, how many days will it take 10 workers to complete the same job?
- 15 days
- 18 days
- 21 days
- None of these
Explanation
Work (in worker-days) = 15 × 12 = 180
Days for 10 workers = 180 ÷ 10 = 18 days.