A can complete a work alone in 10 days. A & B together complete it in 8 days. How many days can B alone complete the same work?
- 30 days
- 40 days
- 20 days
- 25 days
Explanation
Step 1: A’s 1-day work
Step 2: A + B’s 1-day work
Step 3: B’s 1-day work
Find LCM of 8 and 10 = 40:
Step 4: Days B alone will take