• Call Us : 03082533000 (WhatsApp)
  • Email Us : TestPointpk.com@gmail.com
Sticky Note
If 4 workers finish a task in 6 days, 3 workers will finish in?
  1. 10
  2. 8
  3. 7
  4. None of these
Explanation

4 workers finish in 6 days

1 worker will finish in 4 × 6 = 24 days

3 workers will finish in 24/3 = 8 days

Related MCQs

  1. 800
  2. 500
  3. 600
  4. 400
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 32:35
  2. 32:37
  3. 32:39
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 77:96
  2. 75/95
  3. 73/94
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 60:77
  2. 6:7
  3. 8:9
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 3:4
  2. 2:3
  3. 5:3
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

Leave a Reply

Your email address will not be published. Required fields are marked *

1 + 2 = ?



All Rights Reserved © TestPointpk.com