In a bank there are 8 people. A financial issue has come up which will take the regular staff 36 hours to resolve the issue. Considering all the staff work at the same pace, how many additional workers would be needed to complete the work in 8 hours?
- 36
- 8
- 28
- 18
Explanation
Work = Number of workers × Time
Let’s find the total work in worker-hours:
- 8 workers × 36 hours = 288 worker-hours
Now, to finish the work in 8 hours, let’s find how many total workers are needed:
- 288 ÷ 8 = 36 workers
We already have 8 workers, so additional workers needed:
- 36 − 8 = 28
Related MCQs
- 30 km/h
- 40 km/h
- 50 km/h
- 60 km/h
اس سوال کو وضاحت کے ساتھ پڑھیں
- 40 km/h
- 50 km/h
- 60 km/h
- 70 km/h
اس سوال کو وضاحت کے ساتھ پڑھیں
- 30 km
- 35 km
- 36.67 km
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 0.6
- 0.7
- 0.8
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 5:35 am
- 5:15 pm
- 5:35 pm
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
Leave a Reply
Your email address will not be published. Required fields are marked *