120 men can complete a work in 90 days. In how many days will 270 men complete the same work?
  1. 45 days
  2. 50 days
  3. 40 days
  4. 30 days
Explanation

Work is inversely proportional to the number of men.  

So,  

(120 men × 90 days) = (270 men × x days)  

⇒ 10800 = 270x  

⇒ x = 10800 / 270  

⇒ x = 40 days