If A and B together complete a work in 12 days and B alone can do it in 20 days, how many days will A alone take to complete the work?
  1. 30 days
  2. 25 days
  3. 28 days
  4. None of these
Explanation

Let's denote A's rate of work as A, and B's rate of work as B.

Given A + B together complete the work in 12 days:

(A + B)'s 1 day's work = 1/12

B alone completes the work in 20 days:

B's 1 day's work = 1/20

A's 1 day's work = (A + B)'s 1 day's work - B's 1 day's work

= 1/12 - 1/20

= (5 - 3) / 60

= 2 / 60

= 1 / 30

A alone will complete the work in 30 days.

Related MCQs

  1. 12 years
  2. 13 years
  3. 14 years
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 30
  2. 35
  3. 40
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 15
  2. 16
  3. 17
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 50
  2. 60
  3. 70
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 18 years
  2. 20 years
  3. 22 years
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

Leave a Reply

Your email address will not be published. Required fields are marked *

1 + 2 = ?



All Rights Reserved © TestPointpk.com