If 5 workers can finish a task in 4 days, how many days will it take 10 workers to finish the same task?
  1. 2 days
  2. 4 days
  3. 6 days
  4. 8 days
Explanation

Given:

  • 5 workers → 4 days
  • 10 workers →? days

Using the formula:

Workers × Days = Constant

5 x 4 = 10 x X 

20 = 10x

x=20/10 

x = 2 days 


Related MCQs

  1. 2 km
  2. 3 km
  3. 4 km
  4. 5 km
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 47 km/h
  2. 46 km/h
  3. 48 km/h
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 4 kilometers
  2. 5 kilometers
  3. 7 kilometers
  4. None of above
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 50 km/hour
  2. 100 km/hour
  3. 150 km/hour
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 3 hours 30 minutes, treating the speed change as extra delay.
  2. 3 hours 18 minutes, being 48 + 48 12 minutes plus 1 hour 30 minutes.
  3. 2 hours 48 minutes, using an overall average speed.
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

All Rights Reserved © TestPointpk.com