If 5 workers can finish a task in 4 days, how many days will it take 10 workers to finish the same task?
- 2 days
- 4 days
- 6 days
- 8 days
Explanation
Given:
- 5 workers → 4 days
- 10 workers →? days
Using the formula:
Workers × Days = Constant
5 x 4 = 10 x X
20 = 10x
x=20/10
x = 2 days
Related MCQs
- 2 km
- 3 km
- 4 km
- 5 km
اس سوال کو وضاحت کے ساتھ پڑھیں
- 47 km/h
- 46 km/h
- 48 km/h
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 4 kilometers
- 5 kilometers
- 7 kilometers
- None of above
اس سوال کو وضاحت کے ساتھ پڑھیں
- 50 km/hour
- 100 km/hour
- 150 km/hour
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 3 hours 30 minutes, treating the speed change as extra delay.
- 3 hours 18 minutes, being 48 + 48 12 minutes plus 1 hour 30 minutes.
- 2 hours 48 minutes, using an overall average speed.
- None of these