If a person A completes a work in 12 days and person B in 6 days and they start working together then In how many days they will complete the work?
- 4
- 3
- 5
- None of these
Explanation
Person A completes the work in 12 days, so their work rate is 1/12 of the work per day.
Person B completes the work in 6 days, so their work rate is 1/6 of the work per day.
When they work together, their combined work rate is the sum of their individual work rates:
(1/12 + 1/6) = (1/12 + 2/12) = 3/12 = 1/4 of the work per day.
Since they can complete 1/4 of the work in a day, they will complete the entire work in: 4 days.
Related MCQs
- 39 ÷ 4 = 9 R3, 39 ÷ 9 = 3 R6
- 39 ÷ 4 = 9 R3, 39 ÷ 9 = 4 R3
- 39 ÷ 4 = 8 R7, 39 ÷ 9 = 4 R3
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 47 years
- 57 years
- 37 years
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 12 years
- 13 years
- 14 years
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 30
- 35
- 40
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 15
- 16
- 17
- None of these