If 42 women can do a work in 18 days, how many women will do the same work in 21 days?
  1. 18
  2. 12
  3. 24
  4. 36
Explanation

To find the answer, we calculate the total work:

42 women x 18 days = 756 woman-days

Since the work remains the same, we divide the total work by 21 days:

756 woman-days ÷ 21 days = 36 women

So, 36 women can do the same work in 21 days.

Related MCQs

  1. 3 hours 30 minutes, treating the speed change as extra delay.
  2. 3 hours 18 minutes, being 48 + 48 12 minutes plus 1 hour 30 minutes.
  3. 2 hours 48 minutes, using an overall average speed.
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 60 minutes
  2. 90 minutes
  3. 108 minutes
  4. 120 minutes
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 10 minutes
  2. 15 minutes
  3. 20 minutes
  4. 25 minutes
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 6
  2. 8
  3. 10
  4. 12
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 9:10 a.m.
  2. 9:15 a.m.
  3. 9:20 a.m.
  4. 9:30 a.m.
اس سوال کو وضاحت کے ساتھ پڑھیں

All Rights Reserved © TestPointpk.com