20 men can do a work in 5 days. How many days will 10 men take to complete that work?
20 آدمی 18 دن میں کام مکمل کرتے ہیں، پھر 10 آدمی کام مکمل کر سکتے ہیں۔
  1. 36 days
  2. 10 days
  3. 12 days
  4. 16 days
Explanation
If 20 men can complete a work in 5 days, it means that the total work can be represented as:

Total Work=20 men×5 days

Now, if we want to find out how many days it will take for 10 men to complete the same work, we can set up the equation like this:

Total Work=10 men×number of days (we want to find)

Since the total work remains the same in both cases, we can equate the two expressions:

20 men×5 days=10 men×number of days

20×5=10×number of days

100=10×number of days

Divide both sides by 10:

Number of days=10010=10 days

So, 10 men would take 10 days to complete the work.

Related MCQs

  1. 30 km
  2. 35 km
  3. 36.67 km
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 0.6
  2. 0.7
  3. 0.8
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 5:35 am
  2. 5:15 pm
  3. 5:35 pm
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 350 km
  2. 300 km
  3. 400 km
  4. 450 km
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 20 days
  2. 30 days
  3. 40 days
  4. 50 days
اس سوال کو وضاحت کے ساتھ پڑھیں

Leave a Reply

Your email address will not be published. Required fields are marked *

1 + 2 = ?



All Rights Reserved © TestPointpk.com