10 workers complete work in 40 days, 20 workers complete work in how many days?
- 10 days
- 20 days
- 5 days
- None of these
Explanation
We are given that 10 workers complete the work in 40 days.
Step 1: Find total work in worker-days
Total work = 10 workers × 40 days = 400 worker-days
Step 2: Find time for 20 workers
Time required = 400 worker-days ÷ 20 workers
= 20 days