4 mat-weavers can weave 4 mats in 4 days. At the same rate, how many mats would be woven by 8 mat-weavers?
- 8
- 16
- 12
- None of these
Explanation
Given:
- 4 weavers weave 4 mats in 4 days
- So, each weaver weaves 1 mat in 4 days
Now, you have 8 weavers working at the same rate.
If 1 weaver weaves 1 mat in 4 days, then:
- 8 weavers will weave 8 mats in 4 days