Hamza can do a work in 15 days and Aslam in 12 days. If they work on it together for 4 days, the fraction of work that is left is________?
  1. 2/5
  2. 3/5
  3. 4/7
  4. 1/5
  5. 1/4
Explanation


Part of work completed by Hamza in a day = 1/15 Part of work completed by Aslam in a day = 1/12 Part of work completed by them in a day = (1/15)+(1/12) = 3/20 Part of work completed by them in 4 days = (3/20)*4 = 3/5 Fraction of work left

= 1-(3/5)
= 2/5

Related MCQs

  1. Rs. 3000
  2. Rs.1800
  3. Rs.2000
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 5.5
  2. 4.5
  3. 5
  4. 6None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. Century
  2. Millennium
  3. Bicentennial period
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 12
  2. 14
  3. 16
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. n(n + 1)2
  2. 2n
  3. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

All Rights Reserved © TestPointpk.com