If actual cost is high but earned value is low, the project status is?
  1. Under budget and ahead of schedule
  2. Over budget and behind schedule
  3. On budget and on schedule
  4. Cannot determine
Explanation
  • Actual Cost (AC) measures money spent so far.
  • Earned Value (EV) measures the value of work actually completed.
  • If AC > EV, the project is spending more than the value earned → over budget.
  • If EV is low, less work is completed than planned → behind schedule.
  • Related MCQs

    1. 2
    2. 5
    3. 6
    4. 7
    اس سوال کو وضاحت کے ساتھ پڑھیں

    تعددی تقسیم میں بائیں طرف لمبی اور دائیں طرف چھوٹی دُم ہونے کا کیا مطلب ہے؟
    1. Positively skewed distribution
    2. Negatively skewed distribution
    3. Normal distribution
    4. None of these
    اس سوال کو وضاحت کے ساتھ پڑھیں

    1. 0.2
    2. 0.3
    3. 0.4
    4. None of these
    اس سوال کو وضاحت کے ساتھ پڑھیں

    1. 1
    2. 2
    3. 3
    4. None of these
    اس سوال کو وضاحت کے ساتھ پڑھیں

    1. Mean
    2. Median
    3. Mode
    4. None of these
    اس سوال کو وضاحت کے ساتھ پڑھیں

    All Rights Reserved © TestPointpk.com