Work done by 40 men in 40 days = 1/3 of total work
Total work = 3 × (40 × 40) = 4800 man-days
Remaining work = 2/3 of total work = 3200 man-days
Time left = 50 days
Men required = 3200 ÷ 50 = 64 men
Additional men needed = 64 − 40 = 24 men