If 28 workers can complete a task in 26 days. The number of workers required to complete the task in 13 days is?
- 64
- 56
- 48
- None of these
Explanation
Let's solve this:
Work = Force × Time (or Workers × Days)
28 workers × 26 days = x workers × 13 days
x = (28 × 26) / 13
x = 56 workers
Related MCQs
- 32:35
- 32:37
- 32:39
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 77:96
- 75/95
- 73/94
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 60:77
- 6:7
- 8:9
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 3:4
- 2:3
- 5:3
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 9:4
- 2:3
- 8:12
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
Leave a Reply
Your email address will not be published. Required fields are marked *