If 28 workers can complete a task in 26 days. The number of workers required to complete the task in 13 days is?
- 64
- 56
- 48
- None of these
Explanation
Let's solve this:
Work = Force × Time (or Workers × Days)
28 workers × 26 days = x workers × 13 days
x = (28 × 26) / 13
x = 56 workers