If 24 employees can complete a project in 20 days. The number of employees required to complete the project in 40 days is ______?
- 12
- 17
- 24
- None of these
Explanation
Inverse proportion: more days, fewer employees
24 employees × 20 days = x employees × 40 days
x = (24 × 20)/40
x = 12