If 30 workers can complete a task in 20 days. The number of workers required to complete the task in 40 days is?
- 12
- 15
- 20
- None of these
Explanation
Let's use the inverse proportion:
30 workers × 20 days = x workers × 40 days
x = (30 × 20) / 40
x = 15