If 12 employees take 20 days to complete a project, the number of employees needed to complete it in 10 days is?
- 18
- 22
- 24
- None of these
Explanation
Let's apply inverse proportion:
12 employees × 20 days = x employees × 10 days
x = 12 × 20/10 = 24