If six people dig a well 200m deep in 15 days, the number of people that are required to dig the same well in 18 days is _____?
  1. 15
  2. 5
  3. 10
  4. None of these
Explanation

6 people dig a 200m well in 15 days.

To find the total work done in terms of "man-days":

6 people × 15 days = 90 man-days

Now, let's find the number of people required to dig the same well in 18 days:

Let x be the number of people required.

x people × 18 days = 90 man-days

x = 90 / 18

x = 5

Related MCQs

  1. 25
  2. 35
  3. 45
  4. 55
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 50 worker-days
  2. 60 worker-days
  3. 65 worker-days
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 50
  2. 45
  3. 40
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 5 km
  2. 3 km
  3. 4 km
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 2 km
  2. 3 km
  3. 4 km
  4. 5 km
اس سوال کو وضاحت کے ساتھ پڑھیں

All Rights Reserved © TestPointpk.com