5 men can do a work in 50 days. How long will it take 3 men to complete the work?
- 80 days
- 82 days
- 83 days
- 85 days
Explanation
5 men = 50 days1 man = 5 × 50 = 250 days
3 men = 250/3 = 83.33 days
Last verified on 02-03-2026