10 women can complete a work in 7 days, and 10 children take 14 days to complete the work. How many days will 5 women and 10 children take to complete the work?
- 8 days
- 7 days
- 6 days
- Cannot be determined
Explanation
Work done by 10 women in 7 days = 1
Work done by 1 woman in 7 days = 1/10
Work done by 1 woman in 1 day = 1/(10 × 7) = 1/70
Work done by 10 children in 14 days = 1
Work done by 1 child in 14 days = 1/10
Work done by 1 child in 1 day = 1/(10 × 14) = 1/140
Work done by 5 women in 1 day = 5 × 1/70 = 5/70 = 1/14
Work done by 10 children in 1 day = 10 × 1/140 = 10/140 = 1/14
Total work done per day = 1/14 + 1/14 = 2/14 = 1/7
Total days required = 7 days
Related MCQs
- 30 km
- 35 km
- 36.67 km
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 0.6
- 0.7
- 0.8
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 5:35 am
- 5:15 pm
- 5:35 pm
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 350 km
- 300 km
- 400 km
- 450 km
اس سوال کو وضاحت کے ساتھ پڑھیں
- 20 days
- 30 days
- 40 days
- 50 days
اس سوال کو وضاحت کے ساتھ پڑھیں
Leave a Reply
Your email address will not be published. Required fields are marked *