• Call Us : 03082533000 (WhatsApp)
  • Email Us : TestPointpk.com@gmail.com
Sticky Note
X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone, and then after 4 days, Y joined him until the completion of the work. How long did the work last?
  1. 10 days
  2. 6 days
  3. 15 days
  4. None of these
Explanation

X can do the work in 20 days, so X's work rate is 1/20 of the work per day.

Y can do the work in 12 days, so Y's work rate is 1/12 of the work per day.

X works alone for 4 days, completing 4/20 = 1/5 of the work.

Y joins X, and together they complete the remaining 4/5 of the work.

Their combined work rate is (1/20 + 1/12) = 8/60 = 2/15 of the work per day.

Since they complete 4/5 of the work together, it takes them (4/5) / (2/15) = 6 days to complete the remaining work.

Adding the 4 days X worked alone, the total duration is 4 + 6 = 10 days.

So, the correct answer is: 10 days.

Related MCQs

  1. 25
  2. 35
  3. 45
  4. 55
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 50 worker-days
  2. 60 worker-days
  3. 65 worker-days
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 50
  2. 45
  3. 40
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 5 km
  2. 3 km
  3. 4 km
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 2 km
  2. 3 km
  3. 4 km
  4. 5 km
اس سوال کو وضاحت کے ساتھ پڑھیں

All Rights Reserved © TestPointpk.com