If 16 workers complete a task in 40 days. The number of workers required to complete the task in 80 days is ____?
- 20
- 8
- 12
- 10
Explanation
More days means less workers needed (inverse relation)16 workers × 40 days = x workers × 80 days
x = (16 × 40)/80 = 8 workers