Two classrooms are to be built in a school and planned that 8 masons and labours shall complete them is 20 days. If the number of workers is increased up to 10, how many days will be taken in the completion of work?
- 26 days
- 36 days
- 16 days
- 15 days
Explanation
8 men can do work = 20 days
1 man can do this work = 8*20
10 men can do that work = [8*20]/10
=16 days
Related MCQs
- 39 ÷ 4 = 9 R3, 39 ÷ 9 = 3 R6
- 39 ÷ 4 = 9 R3, 39 ÷ 9 = 4 R3
- 39 ÷ 4 = 8 R7, 39 ÷ 9 = 4 R3
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 47 years
- 57 years
- 37 years
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 12 years
- 13 years
- 14 years
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 30
- 35
- 40
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 15
- 16
- 17
- None of these