A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work was finished one day earlier. How many days would it have been delayed if 5 more men were not employed?
- 4 day
- 2 day
- 1 day
- None
Explanation
men completed the remaining job in .
Now the same job has to be done by .
We know that,
Required time
Delayed time
Related MCQs
- 39 ÷ 4 = 9 R3, 39 ÷ 9 = 3 R6
- 39 ÷ 4 = 9 R3, 39 ÷ 9 = 4 R3
- 39 ÷ 4 = 8 R7, 39 ÷ 9 = 4 R3
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 47 years
- 57 years
- 37 years
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 12 years
- 13 years
- 14 years
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 30
- 35
- 40
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 15
- 16
- 17
- None of these