15 men were hired to plough a piece if land in 10 days. To complete the same job in three days more number of men is required _____?
- 35
- 40
- 50
- 30
Explanation
15 men × 10 days = M2 × 3 days
M2 = 50
More men = 50 - 15 = 35
Last verified on 08-03-2026