- Uncle
- Father
- Brother
- Grandfather
اس سوال کو وضاحت کے ساتھ پڑھیں
Explanation
A and B are brothers: They share the same parents.
A's son is D's brother: Therefore, A is the father of D.
C and D are sisters: Since A is the father of D, A is also the father of C.
B is A's brother: Since A is C's father, B is C's paternal uncle
Question updated 03-March-2026
- 46
- 48
- 44
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
Explanation
The differences are 5, 7, 9 and 11.
The differences increase by 2 each time.
The next difference is 13, so 35 + 13 = 48.
Last verified on 05-11-2026
- Gallery
- Frame
- Artist
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
Explanation
- Book is created by Author.
- Painting is created by Artist.
Last verified on 12-10-2026
- 3
- 3.375
- 4
- 4.5
اس سوال کو وضاحت کے ساتھ پڑھیں
Explanation
27: 72 = x :9
27/72 = x /9
x = 27 x 9 /72
x = 3.375
Last updated by NA on 04-11-2026
- 18
- 21
- 24
- 30
اس سوال کو وضاحت کے ساتھ پڑھیں
Explanation
Add 6 to each number.
3 + 6 = 9
9 + 6 = 15
15 + 6 = 21
21 + 6 = 27
27 + 6 = 33
Last updated by NA on 04-11-2026
- 67
- 71
- 77
- 81
اس سوال کو وضاحت کے ساتھ پڑھیں
Explanation
Sum:
2+3+5+7+11+13+17+19=77
Correct Answer: 77
- 8.09%
- 9.09%
- 10%
- 12%
اس سوال کو وضاحت کے ساتھ پڑھیں
Explanation
Cost Price = Rs. 44,000
Selling Price = Rs. 48,000
Profit = 48,000 − 44,000 = Rs. 4,000
Formula:
Profit % = profit cost price x 100
= 4000 44000 x 100
= 9,09 %
Last updated by NA on 04-11-2026
دیئے گئے نمبر کے مربع جڑ کا اخراج کیا ہے؟
- Binary operation
- Relation
- Unary operation
- Relation in some set
اس سوال کو وضاحت کے ساتھ پڑھیں
- 10%
- 20%
- 25%
- 30%
اس سوال کو وضاحت کے ساتھ پڑھیں
Explanation
Given that:
C.P=450 & S.P=495
When S.P is greater than C.P, we get Profit
Profit=S.P-C.P
Profit=495-450
Profit = 45
Now,
Gain% = [100*Gain]/C.P
= [100*45]/450
= 10%
***
Last updated by NA on 04-11-2026
- 50 days
- 35 days
- 40 days
- 45 days
اس سوال کو وضاحت کے ساتھ پڑھیں
Explanation
120 men can do work = 30 days
1 man can do this work = 120 x 30 = 3600 days
80 men can do this work = 3600/80 = 45 days
Last updated by NA on 04-11-2026