If A can complete a piece of work in 6 hours and B can complete the same work in 4 hours, and both work together for 2 hours, how much more time will A alone require to finish the remaining work?
  1. 1 hour
  2. 30 minutes
  3. 45 minutes
  4. None of these
Explanation

A's rate = 1/6, B's rate = 1/4; together = 5/12 of the work per hour.

In 2 hours, they complete 10/12 = 5/6 of the work, leaving 1/6.

A alone completes 1/6 of the work in 1 hour.


Verified & Updated

Related MCQs

  1. 1 hour
  2. 30 minutes
  3. 45 minutes
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 24
  2. 12
  3. 36
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 11th Floor
  2. 12th Floor
  3. 13th Floor
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 24
  2. 26
  3. 28
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 5
  2. 4
  3. 3
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

All Rights Reserved © TestPointpk.com