If 4 workers finish a task in 6 days, 3 workers will finish in?
  1. 10
  2. 8
  3. 7
  4. None of these
Explanation

4 workers finish in 6 days

1 worker will finish in 4 × 6 = 24 days

3 workers will finish in 24/3 = 8 days