If 16 men take 20 days to complete a work. The number of men will complete the work in 40 days is ____?
  1. 6
  2. 8
  3. 10
  4. None of these
Explanation

M1 × D1 = M2 × D2

16 × 20 = M2 × 40

M2 = (16 × 20)/40

M2 = 8