If 105 men can complete a work in 45 days, in how many days will 90 men complete the same work (assuming equal efficiency)?
  1. 50 days
  2. 52.5 days
  3. 55 days
  4. 60 days
Explanation

 Work = Men × Days

So,  

105 men × 45 days = 4725 man-days

Now, if 90 men are doing the same work:

4725 man-days ÷ 90 men

= 52.5 days


Related MCQs

  1. 45 km/h
  2. 48 km/h
  3. 50 km/h
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 120 km
  2. 100 km
  3. 140 km
  4. 80 km
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 30 km/h
  2. 40 km/h
  3. 50 km/h
  4. 60 km/h
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 40 km/h
  2. 50 km/h
  3. 60 km/h
  4. 70 km/h
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 30 km
  2. 35 km
  3. 36.67 km
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

Leave a Reply

Your email address will not be published. Required fields are marked *

1 + 2 = ?



All Rights Reserved © TestPointpk.com