If 10 men can construct a building in 40 days. How long will it take 20 men to do this work?
  1. 20 days
  2. 30 days
  3. 40 days
  4. 50 days
Explanation
10 men = 40 days
1 man = 10 × 40 = 400 days
20 men = 400/20 = 20 days

Last verified on 03-04-2026