20 men can construct a building in 40 days. How long will it take 10 men to do this work?
  1. 50 days
  2. 60 days
  3. 70 days
  4. 80 days
Explanation

20 men can construct a building in 40 days.

Total work = 20 men × 40 days = 800 man-days.

Time = Total work / Number of men = 800 man-days / 10 men = 80 days.