12 men can work in 24 days how can doing the 8 men same work on which days?
  1. 34 days
  2. 36 days
  3. 40 days
  4. none of these
Explanation

If 12 men can complete the work in 24 days,

it means that the total number of man-days required to complete the work is:

12 men * 24 days = 288 man-days.

288 man-days / 8 men = 36 days.