A completes a work in 12 days whereas B completes the same work in 24 days. If both A and B work together, the work will be completed in ____?
- 6
- 8
- 10
- 12
Explanation
Work done by A in 1 day = 1/12
Work done by B in 1 day = 1/24
Work done by A + B in 1 day = 1/12 + 1/24
= 2/24 + 1/24
= 3/24
= 1/8
So together they complete 1/8 of the work in 1 day.
Time to complete whole work = 1 / (1/8) = 8 days