36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work?
  1. 22
  2. 24
  3. 26
  4. None of these
Explanation

To find the solution, first, calculate the total man-days required for the job: 36 men * 18 days = 648 man-days.

Then, divide the total man-days by the new number of men (27) to find the new number of days: 648 man-days / 27 men = 24 days.

So, the correct answer is 24.

Related MCQs

  1. Semi group
  2. Subgroup
  3. Cyclic group
  4. Abelian group
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. Milk
  2. Ounce
  3. Liquid
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 10°
  2. 20°
  3. 180°
  4. 220°
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 500
  2. 525.50
  3. 540
  4. 551.25
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. Rs. 1710
  2. Rs. 1690
  3. Rs. 1675
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

Leave a Reply

Your email address will not be published. Required fields are marked *

1 + 2 = ?



All Rights Reserved © TestPointpk.com