If 20 men can do a piece of work in 8 days, then how many men can finish the same work in 10 days?
  1. 15
  2. 17
  3. 18
  4. 16
Explanation
20 men complete the work in 8 days
Total work = 20 men * 8 days = 160 man-days
Now, to complete the work in 10 days:
160 man-days / 10 days = 16 men

Related MCQs

  1. No; only the two largest buses can be counted.
  2. No; the 10% reserve reduces usable capacity below 214.
  3. Yes; total capacity is 240 and 90% of it is 216.
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 35%, after both distributions and the damaged units.
  2. 31.5%, being 720, then 432, then 378 units.
  3. 33%, counting the damage within the afternoon percentage.
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 16
  2. 27
  3. 81
  4. 90
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 1,742.4 cards, being 1,980 less 316.8 plus 79.2.
  2. 1,650 cards, taking 16% of the original stock as the transferred quantity.
  3. 1,742 cards, rounding the fractional result down.
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 280
  2. 300
  3. 320
  4. 340
اس سوال کو وضاحت کے ساتھ پڑھیں

All Rights Reserved © TestPointpk.com