If 20 men can do a piece of work in 8 days, then how many men can finish the same work in 10 days?
- 15
- 17
- 18
- 16
Explanation
20 men complete the work in 8 daysTotal work = 20 men * 8 days = 160 man-days
Now, to complete the work in 10 days:
160 man-days / 10 days = 16 men
Related MCQs
- No; only the two largest buses can be counted.
- No; the 10% reserve reduces usable capacity below 214.
- Yes; total capacity is 240 and 90% of it is 216.
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 35%, after both distributions and the damaged units.
- 31.5%, being 720, then 432, then 378 units.
- 33%, counting the damage within the afternoon percentage.
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 16
- 27
- 81
- 90
اس سوال کو وضاحت کے ساتھ پڑھیں
- 1,742.4 cards, being 1,980 less 316.8 plus 79.2.
- 1,650 cards, taking 16% of the original stock as the transferred quantity.
- 1,742 cards, rounding the fractional result down.
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 280
- 300
- 320
- 340