A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work was finished one day earlier. How many days would it have been delayed if 5 more men were not employed?
- 4 day
- 2 day
- 1 day
- None
Explanation
men completed the remaining job in .
Now the same job has to be done by .
We know that,
Required time
Delayed time
Related MCQs
- 12 years
- 13 years
- 14 years
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 30
- 35
- 40
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 15
- 16
- 17
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 50
- 60
- 70
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 18 years
- 20 years
- 22 years
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
Leave a Reply
Your email address will not be published. Required fields are marked *