A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work was finished one day earlier. How many days would it have been delayed if 5 more men were not employed?
  1. 4 day
  2. 2 day
  3. 1 day
  4. None
Explanation

 men completed the remaining job in .
Now the same job has to be done by .
We know that, 
Required time 
Delayed time 

Related MCQs

  1. 12 years
  2. 13 years
  3. 14 years
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 30
  2. 35
  3. 40
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 15
  2. 16
  3. 17
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 50
  2. 60
  3. 70
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 18 years
  2. 20 years
  3. 22 years
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

Leave a Reply

Your email address will not be published. Required fields are marked *

1 + 2 = ?



All Rights Reserved © TestPointpk.com