If 5 workers can complete a task in 12 days, how many worker-days are required to complete the task?
- 50 worker-days
- 60 worker-days
- 65 worker-days
- None of these
Explanation
Worker-days = Workers × Days
= 5 × 12 = 60 worker-days.
Last verified on 07-09-2026
Related MCQs
- 50 worker-days
- 60 worker-days
- 65 worker-days
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 5 years
- 10 years
- 15 years
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 17.5 years
- 18.5 years
- 19.5 years
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 15 days
- 21⅔ days
- 25 days
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 10 years
- 14 years
- 12 years
- None of these