If 5 workers can complete a task in 12 days, how many worker-days are required to complete the task?
  1. 50 worker-days
  2. 60 worker-days
  3. 65 worker-days
  4. None of these
Explanation

Worker-days = Workers × Days

= 5 × 12 = 60 worker-days.