Find the quantity of cement required for rate analysis of brickwork in 1:5 for 100 cft:
- 2 bags
- 3 bags
- 4 bags
- 5 bags
Explanation
Given:
Brickwork = 100 cft
Mortar ratio = 1: 5
For rate analysis of brickwork, the standard quantity of cement for 100 cft of brickwork in 1:5 mortar is approximately 4 bags.