If 20 labourers complete a piece of work in 8 days and after 4 days, 8 labourers leave the job, how much work has already been completed?
  1. 1/2
  2. 1/3
  3. 1/4
  4. None of these
Explanation

Total work = Number of labourers x Total days  

Total work = 20 x 8 = 160 units  

Work done in first 4 days = 20 labourers x 4 days  

Work done = 80 units  

Fraction of work completed = Work done / Total work  

= 80 / 160  

= 1 / 2  


Verified & Updated

Related MCQs

  1. 1/2
  2. 1/3
  3. 1/4
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 15 days
  2. 18 days
  3. 21 days
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 32nd
  2. 33rd
  3. 34th
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 12 years
  2. 24 years
  3. 36 years
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 48 years
  2. 44 years
  3. 46 years
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

All Rights Reserved © TestPointpk.com