It takes 4 men 14 hours to repair a road. How long will it take 7 men working at the same rate?
- 4 hours
- 7 hours
- 8 hours
- None of these
Explanation
4 men × 14 hours = 7 men × x hours
56 = 7x
x = 56/7 = 8 hours
Last verified on 15-03-2026