If 70 men dig 630 m³ of soil in 5 days, in the same proportion, 80 men can dig the quantity of soil in 10 days?
- 1440 m³
- 1350 m³
- 1500 m³
- None of these
Explanation
Calculating the Rate of Work per Man per Day
Rate = 630/70 × 5 = 630/350 = 1.8 m³/man/day
Calculating the Quantity of Soil for 80 Men in 10 Days
Quantity = 80 men × 10 days × 1.8 m³/man/day
= 80 × 10 × 1.8
= 1440 m³