If Ali completes a particular work in 4 days and Hyder completes the same work in 12 days. How many days will it take if they work together?
  1. 7
  2. 4
  3. 3
  4. None of these
Explanation

Let's calculate their combined work rate:

Ali's rate = 1 work / 4 days = 1/4 work per day

Hyder's rate = 1 work / 12 days = 1/12 work per day

Combined rate = 1/4 + 1/12

= 3/12 + 1/12

= 4/12

= 1/3 work per day

Time to complete the work together = 1 / (1/3)

= 3 days

Related MCQs

  1. 10
  2. 15
  3. 5
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 10 years
  2. 30 years
  3. 20 years
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 2 km
  2. 3 km
  3. 4 km
  4. 5 km
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 40 years
  2. 30 years
  3. 35 years
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 50
  2. 45
  3. 40
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

All Rights Reserved © TestPointpk.com