If 3 men or 6 boys can complete a task in 20 days, how many days will 6 men and 8 boys take to do the same task?
  1. 6
  2. 8
  3. 10
  4. None of these
Explanation

Let's solve:

3 men = 6 boys (given)

1 man = 2 boys

Work done by 3 men or 6 boys in 20 days:

Let's calculate work done by 1 boy in 1 day:

6 boys * 20 days = 120 boy-days

Now, 6 men and 8 boys:

6 men = 6 * 2 = 12 boys

Total = 12 boys + 8 boys = 20 boys

Time taken = 120 boy-days / 20 boys = 6 days

Related MCQs

  1. 2 km
  2. 3 km
  3. 4 km
  4. 5 km
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 40 years
  2. 30 years
  3. 35 years
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 50
  2. 45
  3. 40
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 10
  2. 20
  3. 30
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 95.05 km/h
  2. 105.05 km/h
  3. 115.05 km/h
  4. 125.05 km/h
اس سوال کو وضاحت کے ساتھ پڑھیں

All Rights Reserved © TestPointpk.com