P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in _______ days.
  1. 12
  2. 13
  3. 14
  4. None of these
Explanation

Work done by P in 1 day = 1/15
Work done by Q in 1 day = 1/10
Work done by P and Q in 1 day = 1/15 + 1/10 = 1/6
Work done by P and Q in 2 days = 2 × (1/6) = 1/3
Remaining work = 1 – 1/3 = 2/3
Time taken by P to complete the remaining work 2/3 = (2/3) / (1/15) = 10 days
Total time taken = 2 + 10 = 12 days

Related MCQs

  1. 40
  2. 45
  3. 50
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 20
  2. 20.5
  3. 21
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 6
  2. 8
  3. 10
  4. 12
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 18
  2. 20
  3. 22
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. Rs. 8,000
  2. Rs. 9,000
  3. Rs. 10,000
  4. Rs. 12,000
اس سوال کو وضاحت کے ساتھ پڑھیں

All Rights Reserved © TestPointpk.com