If 15 workers can complete a job in 12 days, how many days will it take 10 workers to complete the same job?
  1. 15 days
  2. 18 days
  3. 21 days
  4. None of these
Explanation

Work (in worker-days) = 15 × 12 = 180

Days for 10 workers = 180 ÷ 10 = 18 days.